Thu 19 Nov 2009
The construction season is now over. Despite an extremely wet October and the presence of ledge rock, we were able to complete Stage 1 of the project by November 6. This is within one week of the original completion date of November 1. The Contractor has removed all traffic control and detour signs until next May. The one exception is the stop sign at 4th Street and 24th Avenue East. This is a temporary sign that will remain through the winter and 2010 construction.
Ulland’s schedule for next year includes resuming construction in mid-May, once the road restrictions are lifted. At that time, we will place the detour route as we had it this year. The detour will remain in place until work is complete through the intersection with St. Marie Street. We will then move the detour to Wallace Avenue from Arrowhead Road to St. Marie Street. At that point, Woodland Avenue from 4th Street to St. Marie Street will be open.
As spring approaches and construction comes closer, we will be updating this blog with a start date and schedule. We will also be holding a resident/business meeting to discuss the 2010 construction schedule.
Salo Engineering, the City of Duluth, and Ulland Brothers would like to extend our appreciation and thanks for everyone’s patience throughout the project. The open communication between owners/businesses and the construction team allowed for a successful and safe project. We look forward to being back in your neighborhood next year to complete Stage 2 of the project.
If anyone has any comments, questions, or concerns, please notify David Bolf or David Salo with Salo Engineering at (218) 727-8796.
See you next year!